88 Fleet Street building works 3.

Written by . Filed under Uncategorized. Bookmark the Permalink. Comments are closed, but you can leave a trackback: Trackback URL.
UPDATE: Progress on glazing, lighting, staircase repairs, carpentry, signage, canteen etc. February 2013

 

     
88 Fleet Street Building Works fortnightly update meeting with on-site contractors. Mid February 2013.
Full report 88 FLEET STREET MEETING NOTES

 


Installation of toughened glass on Floor 1. to get the window seating areas back into use. Completion due early March 2013
 

 

   
The main staircase recovered and brought back into use. Floor 1. stone paving work and replacement nosings. “Poor condition of repaired nosings on the bottom flights between the entrance and the first floor. Chris (on site operative) is to expose the nosing construction on several treads to determine whether repairs could be limited to the 75-100mm wide concrete repairs. Some repairs at least, e.g., half landing nosings, would require a wide repair due to the depression in the centre caused by wear.” Fleet Street Meeting Notes. February 2013

 

Lighting test: Fluorescent ceiling lights following the precise ‘contours’, shape of each room 12” out from the cornices. Test on Floor 3, Fleet Street side. February 2013

 

  
Floor 4. Canteen, cupboards installed, screed, first fix on lighting and electrics. Lighting.  Floor 4. reading lamp.
 
 

Test: Non-slip vinyl flooring for the Floor 4. bathroom. February 2013
 
 


Signage design above and test position. Final design to be ‘installed’ first week March 2013. MDR (n)

 


88 Signage. Base coat. Installation Fleet Street/ Front of building. March 6, 2013

 


88 Signage. Base coat. Installation. St.Brides Yard/Rear of building. March 6, 2013